Home | Projects | FTNx Network Upgrade for Safer Level Crossings

FTNx Network Upgrade for Safer Level Crossings

North Downs Line - Burrows Lane, Brook, Tangley AHB & Chilworth MCB-CCTV

SPEAK TO US

arrow icon

Client | AtkinsRealis

Sector | Rail Telecoms Infrastructure

Location | Surrey, UK

OVERVIEW

As part of Network Rail’s safety upgrade programme, AtkinsRéalis was contracted to deliver GRIP 4–8 stages for the enhancement of signalling and level crossing assets across four key sites on the North Downs Line. To support this, ADComms was engaged to install, test, and commission critical FTNx telecoms infrastructure—enabling robust connectivity for signalling systems and improving operational safety.

This project builds on the trusted partnership between ADComms and AtkinsRéalis, previously established through successful collaboration on the East West Rail (EWR) programme.

Project Main Image
KEY HIGHLIGHTS

KEY HIGHLIGHTS

  • bullet

    Commissioning completed on schedule, with no delays caused by ADComms

  • bullet

    FTNx assets integrated into the live NWR network, enabling reliable signalling connectivity

  • bullet

    Client satisfaction, with AtkinsRéalis indicating interest in future collaboration

  • bullet

    Budget and resource alignment, maintaining expected project margins

  • bullet

    Engineer development, strengthening future delivery capability

  • bullet

    Test equipment validated, refreshing internal circuit testing expertise

  • bullet

    Reputation reinforced, positioning ADComms for future FTNx and signalling projects

SCOPE OF WORKS

ADComms was responsible for the full delivery of FTNx infrastructure, including:

  • bullet

    Site surveys across all locations

  • bullet

    Installation of free-issue FTNx equipment within existing Network Rail REBs

  • bullet

    Site Acceptance Testing (SAT) of installed assets

  • bullet

    Commissioning and integration onto the live NWR network

  • bullet

    Circuit provision testing post-NRT build

  • bullet

    Submission of Health & Safety documentation, including test reports and certificates

  • bullet

    Production of Task Briefing Sheets and Planned Works documentation (Standard, At-Risk, Disconnection)

SCOPE OF WORKS

CHALLENGES

  • bullet

    Rapid mobilisation following bid acceptance, requiring swift production of Work Package Plans and deployment to the site.

  • bullet

    Procurement delays in receiving free-issue equipment, while the fixed handover deadline remained unchanged.

  • bullet

    Circuit testing issues, with some failures due to Network Rail Telecoms (NRT) design queries—resolved through Change Requests and return visits.

  • bullet

    Disconnection works, requiring coordination with AtkinsRéalis to arrange Level Crossing Attendants for safe operations.

  • bullet

    Live infrastructure environment, demanding precision and safety across REBs and signalling rooms.

Project Main Image

OUTCOME

The FTNx upgrade was delivered on time, within budget, and to the high standards expected by both AtkinsRéalis and Network Rail.

Despite early procurement delays and a compressed delivery window, ADComms’ agile project management and experienced engineering team ensured that all milestones were met without compromising safety or quality.