Client | East West Rail Alliance
Sector | Rail Telecoms Infrastructure
Location | London, UK
As part of East West Rail Phase 2, ADComms was engaged by the East West Rail Alliance (EWRA) to enhance fibre resilience at Marylebone Station.
This initiative was critical to ensuring compliance with Network Rail’s telecoms standards (NR/L2/TEL/30160) and to future-proofing the station’s fibre infrastructure.
The project followed ADComms’ successful delivery of FTNx and GSM-R systems for the same programme, reinforcing our role as a trusted delivery partner in complex rail telecoms environments.
ADComms was responsible for the installation, testing, and commissioning of a new 24-core FTN fibre route between key telecoms nodes.
Our scope included:

Fibre jointing and splicing

Cable containment and routing

Confirmatory testing (ILM/OTDR)

Safe removal of legacy fibre routes

Coordination with Network Rail and specialist subcontractors

Deployment of safety-critical staff and logistics management
Marylebone Station, a busy London terminus, presented a unique set of challenges:

Live operational environment with limited access windows

Legacy infrastructure requiring careful decommissioning

Strict compliance with national fibre diversity standards
The goal was to implement a new, resilient fibre route that would ensure diverse routing of FTN core fibres - minimising the risk of service disruption and aligning with modern telecoms resilience requirements.
The project was successfully delivered by a multidisciplinary team of certified professionals, including construction managers, engineers, fibre specialists, and electricians — all working together to ensure safe and efficient delivery.
Collaboration with trusted subcontractors and Network Rail’s FTN Technical Support enabled a controlled and incident-free fibre cutover at Camden Substation.
Despite the complexity of the site and the constraints of working in a live station environment, the project was successfully delivered with zero impact on the wider programme and the fibre rerouting was completed safely, on time, and to a high technical standard.
The new fibre route now provides robust, compliant, and future-ready telecoms infrastructure for Marylebone Station.
“ADComms’ professionalism, flexibility, and problem-solving capabilities were key to the project’s success. Their ability to integrate with our delivery model has laid strong foundations for future collaboration.”
— East West Rail Alliance